RFP for Tulalip Bay Water System Improvements
Schedule A includes construction of approximately 7,700 linear feet of restrained 6-inch-diameter PVC C900 pipe, 40 linear feet of restrained 8-inch-diameter PVC C900 pipe and associated restrained fittings, 124 water service meter assemblies combination of near and far sides, thirty-four 6-inch gate valves, three 8-inch gate valves, nine fire hydrant assemblies, four 2-inch combined air/vac valve assemblies, and five 2-inch blowoff assemblies. The Work also includes four connections to the existing 6-, and 8-inch water system, property restoration, temporary erosion and sediment control, and roadway/trench restoration, located along Hermosa Beach Road and Fryberg Estates.
Schedule B includes construction of approximately 1,140 linear feet of restrained 6-inch-diameter PVC C900 pipe and associated restrained fittings, 17 water service meter assemblies combination of near and far sides, nine 6-inch gate valves, one 2-inch combined air/vac valve assembly, and one 2-inch blowoff assembly. The Work also includes three connections to the existing 6-inch water system, property restoration, temporary erosion and sediment control, and roadway/trench restoration, located along Mission Beach Road and Mission Beach Lane.
Schedule C includes construction of approximately 1,300 linear feet of restrained 12-inch-diameter PVC C900 pipe and associated restrained fittings, five near side water service meter assemblies, one 12-inch gate valve, two fire hydrant assembly, two 12-inch tapping sleeve and valve assemblies. The Work also includes property restoration, temporary erosion and sediment control, and roadway/trench restoration, located along 88th Street NE.
The project is located on the Tulalip Indian Reservation.
Nicole Smith, Senior Project Manager
Phone: 360-716-4697
Email: nicolesmith@tulaliptribes-nsn.gov
Friday, August 22, 2025, at 8:00 AM PST
Close Date:Wednesday, September 17, 2025 at 2:00 PM PST